Case study · EV Hub · Milton Keynes
24 charge points, fully WCS-funded.
A multi-tenant business park with five different employer schemes to coordinate, a substation already at capacity, and a 12-week deadline. Smart load management did the heavy lifting.
24
Charging Points
168kW
Total Capacity
500+
Staff Supported
£8,400
WCS Funding
The Challenge
A multi-tenanted business park in Milton Keynes with 500+ employees across several corporate occupiers needed to address growing demand for workplace EV charging. Key challenges included:
- Limited existing electrical infrastructure
- Multiple tenants with different charging needs
- Need to avoid expensive DNO upgrades
- Requirement for fair access and billing between tenants
- Future-proofing for increasing EV adoption
Staff surveys indicated that over 30% of employees already owned EVs or planned to purchase one within 12 months, making workplace charging a priority for tenant retention.
Our Solution
We designed a comprehensive workplace charging solution with smart load management to maximise charging capacity within the existing electrical supply:
Charging Infrastructure
- 20 x 7kW AC chargers - Dual-socket units for staff all-day charging
- 4 x 22kW AC chargers - Faster charging for visitors and short stays
- Smart load management - Dynamic load balancing across all chargers
- RFID access control - Secure access for registered staff
- Back-office system - Usage tracking and billing per tenant
Smart Load Management
The intelligent load management system ensures the site never exceeds its available capacity while maximising charging for users:
- Real-time monitoring of building electrical load
- Dynamic allocation of available capacity to chargers
- Priority scheduling based on booking times
- Automatic load shedding during peak building demand
Technical Specifications
Charger Details
- 20 x Alfen Eve Double Pro-line (7kW dual)
- 4 x Alfen Eve Single Pro-line (22kW)
- Total capacity: 168kW
- Managed capacity: 100kW max
- Socket type: Type 2
- OCPP 1.6 compliant
Back Office
- Cloud-based management platform
- Per-tenant usage reporting
- Staff RFID registration
- Mobile app for staff
- Real-time availability display
- Automated billing integration
Results
Six months after installation, the charging hub is fully utilised and delivering value:
95%
Average daily utilisation
150+
Registered EV drivers
12,000kWh
Monthly energy delivered
Financial Summary
- Total investment: £62,000
- Workplace Charging Scheme funding: £8,400 (24 x £350)
- Net investment: £53,600
- Monthly charging revenue: £2,400
- Enhanced tenant satisfaction - Reported as top workplace benefit
Client Feedback
"The smart load management was the key to making this project viable. We were able to install 24 chargers within our existing electrical supply, and the per-tenant billing has made cost recovery straightforward."